The following tables summarize the project schedule for each Comp Plan Element.
The schedule was developed based upon connection between elements, availability of data and other research and planning efforts and amount of work estimated to complete each component.
Comprehensive Plan Update Schedule October 2007 – October 2008
|
Oct-07 |
Nov-07 |
Dec-07 |
Jan-08 |
Feb-08 |
Mar-08 |
Apr-08 |
May-08 |
Jun-08 |
Jul-08 |
Aug-08 |
Sept-08 |
Economic Development Element |
X |
X |
X |
X |
X |
Draft |
|
|
|
|
|
|
Transportation Element |
X |
X |
X |
X |
X |
Draft |
|
|
|
|
|
|
Land Use Element |
X |
X |
X |
X |
X |
Draft |
|
|
|
|
|
|
Housing Element |
|
|
|
|
|
|
X |
X |
X |
X |
X |
Draft |
Natural Resources Element |
|
|
|
|
|
|
X |
X |
X |
X |
X |
Draft |
Cultural Resources Element |
|
|
|
|
|
|
X |
X |
X |
X |
X |
Draft |
Comprehensive Plan Update Schedule October 2008 – November 2009
|
Oct-08 |
Nov-08 |
Dec-08 |
Jan-09 |
Feb-09 |
Mar-09 |
Apr-09 |
May-09 |
Jun-09 |
Jul-09 |
Aug-09 |
Sept-09 |
Oct-09 |
Nov-09 |
Community Facilities Element |
X |
X |
X |
X |
Draft |
|
|
|
|
|
|
|
|
|
Recreation Element |
X |
X |
X |
X |
Draft |
|
|
|
|
|
|
|
|
|
Population Element |
X |
X |
X |
X |
Draft |
|
|
|
|
|
|
|
|
|
Priority Investment Element |
X |
X |
X |
X |
X |
X |
X |
X |
X |
Draft |
|
|
|
|
Design Element |
|
|
|
|
|
X |
X |
X |
X |
Draft |
|
|
|
|
Hazard Mitigation Element |
|
|
|
|
|
X |
X |
X |
X |
Draft |
|
|
|
|
Energy Element (if directed) |
|
|
|
|
|
X |
X |
X |
X |
Draft |
|
|
|
|
Comprehensive Plan – Final |
|
|
|
|
|
|
|
|
|
|
CPC |
PC |
P&DS |
TC |
Drafts of each Comp Plan Element will be reviewed by the Comp Plan Committee, Planning Commission and Planning & Development Standards Committee in sets following the timeline above. (i.e. Economic Development, Transportation and Land Use Elements will be moved forward concurrently). Upon approval from P&DS the elements will be held in final draft form and parked until the entire plan is complete. Upon completion of the final set of elements the entire Comp Plan will be presented to Town Council for adoption.
Organization Structure for Comprehensive Plan Elements
Comp Plan Element |
Staff Lead/Support |
Stakeholders |
Economic Development - Ennis |
Shawn, Marcy |
State/Local Econ. Dev. orgs, Chamber of Commerce, LCOG, Developers, Realtors |
Land Use – Crews |
Marcy, Heather |
Beaufort Co., Bluffton, Developers, SBCRP Land Use Committee |
Transportation - Leary |
Shawn, Randy, Darrin S. |
SCDOT, SBCRP Trans. Committee, Beaufort County, CTC, LRTA, LCOG |
Housing - Crews |
Marcy, Shea, Heather assist |
State and local housing organizations, SC Dept of Commerce, Habitat for Humanity, developers, realtors |
Cultural Resources - Leary |
Jayme, Shawn |
State and local preservation associations, Arts and Cultural Council |
Natural Resources - Varley |
Natural Resources Staff, Shea assist |
State and local regulatory organizations, SBCRP Nat. Resources Committee |
Population - TBD |
Shawn, Nicole |
School District, SCDOT, Beaufort Co., developers, realtors |
Community Facilities - TBD |
Mike, Shawn, CIP work group |
School District, Public Service Districts, utility providers, Beaufort Co. |
Recreation - TBD |
Marcy, Heather |
State and local recreation organizations, Island Rec. Assoc. |
Community Design - TBD |
Ed, Shea, Mike assist |
DRB, Architectural Review Boards, design professionals, developers, realtors |
Priority Investment – TBD |
Shea, Shawn, Marcy, Darrin CIP work group |
Beaufort Co., Bluffton, Public Service Districts, School District, utility providers, transportation groups, |
Hazard Mitigation Plan – TBD |
Trudie, Shawn, Jayme |
Beaufort Co., FEMA, Army Corp, utility providers, emergency services |
Energy – TBD (if directed) |
Shawn, Jayme |
PEC, SCE&G, Utilities |
|