| Description
of Proposed Project |
Implementation
Schedule
|
|
1
- 2
yrs.
|
3
- 6
yrs.
|
7
- 10
yrs.
|
|
3.1
|
Realign
and extend Nassau Street toward the east to connect with Pope Avenue
at Lagoon Road, to provide improved traffic flow from the neighborhoods
southwest of Pope Avenue and reduce traffic on Coligny Circle. |
|
|
|
|
3.2
|
Realign
Pope Avenue from Cordillo Parkway to Coligny Circle and install a
landscaped buffer and a pathway on the northeast side of the road
in order to improve vehicular and pedestrian access and to improve
the aesthetics of the roadway. If feasible, include bio-retention
facilities to improve stormwater quality. |
|
|
|
|
3.3
|
Construct
a pathway on the south side of Pope Avenue from Cordillo Parkway to
Coligny Circle to improve pedestrian access. (In Ten
Year CIP) |
|
|
|
|
3.4
|
Bury
the power lines along Pope Avenue from Cordillo Parkway to Lagoon
Road to improve the aesthetics of the roadway and protect these facilities
during storm events. |
|
|
|
|
3.5
|
Redesign
the Pope Avenue/Lagoon Road intersection, possibly utilizing a traffic
signal, to provide safe pedestrian movement and improved left turn
vehicular movement from Pope Avenue to Lagoon Road.
|
|
|
|
|
3.6
|
Develop
public parking north of Pope Avenue as an integral part of an overall
redevelopment plan for the area. |
|
|
|
|
3.7
|
Redesign
existing public parking and build a parking structure in conjunction
with a park on Town owned property at Coligny Beach Parking. This
will increase the number of parking spaces available for the area
and will be designed to minimize impervious surfaces thereby reducing
stormwater runoff. The new public park will take advantage of existing
trees and will include stormwater facilities which enhance the aesthetics
of the park by providing water features which are attractive as well
as functional. (In Ten Year CIP) |
|
|
|
|
3.8
|
Bury
the power lines along Lagoon Road to improve the aesthetics of the
roadway and protect these facilities during storm events. |
|
|
|
|
3.9
|
Redesign
Coligny Circle, the entrance to Coligny Beach Park, and the two metered
parking lots along the edge of the circle to enhance vehicular and
pedestrian movement in the area. The entrance to the beach park and
the two parking lots will be designed with unique paving, signage,
landscaping, and public art to better identify the drop off area and
entrance to the beach access. |
|
|
|
|
3.10
|
Redesign
Coligny Beach Park to open up the area for pedestrians, relocating
the Town office currently at the park and improving the existing bathroom
facilities to better serve the public. |
|
|
|
|
3.11
|
Bury
the power lines along Avocet Road to improve the aesthetics of the
roadway and protect these facilities during storm events. |
|
|
|