Additional Details for Coligny Area Roadway Improvements

Status:   Under Construction   Under Construction Icon
Project Updates
  • What Happened the Week Ending January 18, 2019

    • Pavement installation on Pope Avenue for the left turn lane at the Park entrance
    • Relocation of the Palmetto Electric line in conflict completed and existing line de-energized
    • Tree removal began on Tanglewood Drive
    • Curb and gutter removed in the median of Pope Avenue
    • Existing waterline to be relocated for new traffic mast arms located
    • Stormwater pipe delivered to site
    • Construction entrance stabilized from Nassau Street to the Coligny Beach Parking lot

    What’s Happening the Week of January 21, 2019

    • Stormwater drainage infrastructure boxes to be delivered and installed on the eastbound lane of Pope Avenue
    • Full depth patching on Pope Avenue to continue at the Pope Avenue / Cordillo Parkway / Shipyard Drive intersection and Pope Avenue eastbound turn lane towards Executive Park Rd
    • Tree removal on Tanglewood Drive and potentially South Forest Beach Drive
    • Casing for foundations for new traffic signal mast arms to be constructed
    • Preparing for waterline relocation and mast arm foundations for the new traffic signal at Pope Avenue and Lagoon Road / Park entrance
  • What Happened the Week Ending January 11, 2019

    • Tree Removal on Pope Avenue for the right turn lane from Pope Ave to the entrance of the Park
    • Median Removal on Pope Avenue for the left turn lane at the Park entrance
    • Palmetto Electric work near completion

    What's Happening the Week of January 14, 2019

    • Pathway closure on Pope Avenue in the eastbound direction from Nassau Street to Coligny Circle
    • Completion of tree removal on Pope Avenue for the intersection of Pope Ave and Lagoon Road
    • Tree Removal on South Forest Beach Drive and Tanglewood Drive
    • Work on the Pope Avenue left turn lane into the Park entrance at Lagoon Road
    • Storm Drainage Infrastructure to be installed on the eastbound lane of Pope Ave
    • Completion of the Palmetto Electric relocation line
  • 1/9/2019 - Pope Avenue Lane Closures
    The pathway along Pope Avenue from Nassau Street to Coligny Circle adjacent to the Coligny Beach parking lot will be closed for several months, starting Thursday, January 10th. more information...
  • What Happened the Week Ending December 21, 2018

    • Tree removal work on Nassau Street was completed minus a few trees to be taken down once the electrical line relocation is completed.
    • Relocation of Palmetto Electric work near completion.
    • Tree removal on Pope Avenue, Tanglewood Drive, and South Forest Beach Drive has not started.

    What;s Happening the Weekof January 7, 2019

    Additional construction crews are coming in the area to begin storm drainage infrastructure on Pope Avenue and the Coligny Beach Parking Lot.
  • 12/14/2018 - Pope Avenue Lane Closures
    There will be temporary daytime lane closures on Pope Avenue at the intersection of Lagoon Road from Monday, December 17 through Thursday, December 20, weather permitting. During this period, crews will be removing trees for construction work at the intersection at Pope Avenue and Lagoon Road. more information...
  • What Happened the Week Ending December 14, 2018

    • Tree Removal on Nassau Street
    • Asphalt Full Depth Patching on Pope Avenue
    • Conduit installation for relocation of Palmetto Electric lines

    What’s Happening the Week of December 17, 2018

    • Tree Removal on Pope Avenue and Lagoon Road (lane closures on Pope Ave)
    • Tree Removal on Nassau Street and Tanglewood Drive
    • Conduit installation for relocated of Palmetto Electric Lines
  • 12/12/2018 - Pope Avenue Lane Closures
    Pavement patch work will continue through Thursday, December 13, weather permitting, on Pope Avenue. This work was originally scheduled to be complete by Wednesday, December 12, but is being extended. Be careful as there will be some lane closures related to this project. The locations of the asphalt patching are designated in red on the below PDF and areas that are complete are noted.

    Pope Ave Asphalt Patch Locations Mapspdf icon

    Other Project Work Happening This Week
    There will be tree removal work on Nassau Street, Tanglewood Drive, and South Forest Beach Drive.

  • What Happened the Week Ending December 7, 2018

    • Trees Removed behind Coligny Beach Parking Lot
    • Tree Removal on Nassau Street
    • Asphalt Full Depth Patching on Pope Avenue began (lane closures on Pope Ave)

    What's Happening the Week of December 10, 2018

    • Continued asphalt full depth patching on Pope Avenue (lane closures on Pope Ave)
    • Tree Removal on Nassau Street, Tanglewood Drive, and South Forest Beach Drive

    Pope Ave Asphalt Patch Locations Maps

  • What Happened the Week Ending November 30, 2018

    • Tree Removal for Relocation of Palmetto Electric power lines
    • Marking of trees to be removed for roadway projects
    • Marking of full depth asphalt patching for Pope Ave resurfacing

    What's Happening Next Week

    • Tree Removal Lagoon Road extension / Park entrance and Nassau Street Reconstruction
    • Full-depth asphalt patching on Pope Avenue, in advance of resurfacing
  • What Happened the Week Ending November 2, 2018

    • Utility Coordination with Palmetto Electric conducted to relocate existing electrical lines in conflict with new electrical lines that will run through the new Low Country Celebration Park.
    • Coordination with the contractor for additional tree removal that was allocated for the Park to assist in stormwater removal.

    What’s Happening the Week Ending November 9, 2018

    • Tree Removal on Coligny Beach parking lot and Nassau Street
  • What Happened the Week Ending October 26, 2018

    • Construction staking on Coligny Beach parking lot for the intersection of Pope Ave and Lagoon Rd completed.
    • Sediment and Erosion Control and Tree Protection in place on Coligny Beach parking lot for the intersection of Pope Ave and Lagoon Rd.
    • Pre-Clear Inspection completed for work to occur on Coligny Beach parking lot and tree removal construction entry between Nassau Street and Coligny beach parking lot.
    • Tree protection fence installed on Nassau Street and trees marked on Tanglewood Drive for tree protection or removal.
    • Utility coordination with Palmetto Electric and SIPSD for new stormwater infrastructure conducted.

    What's Happening Next Week

    • Tree Removal on Coligny Beach parking lot and between Coligny Beach parking lot and Nassau Street
    • Pre-Clear Inspections for Nassau Street
  • 10/3/2018 - Pope Avenue Entrance to Coligny Beach Parking Lot Closed for Improvements
    As part of the Coligny area roadway improvements project, the Pope Avenue entrance to the Coligny Beach parking lot will be closed until further notice. During this time, the parking lot must be accessed from South Forest Beach Drive. more information...
  • 9/21/2018 - The Town has awarded a construction contract to Quality Enterprises USA for $4.8M, to construct area transportation and infrastructure improvements related to the Lowcountry Celebration Park. The Notice To Proceed with work was issued on September 4, 2018. The transportation work will be broken into phases, each with its own schedule, as shown in the exhibit. The Town will hold a public information meeting on the projects Monday, September 24, 5:00 PM in the Council Chambers of Town Hall. This meeting is being held to disseminate project information regarding construction and schedules for the transportation work and the park. The Town will solicit bids for the construction of the Lowcountry Celebration Park this winter. Construction of that project is expected to last from March, 2019 through May, 2020.
  • 8/29/2018 - Project was successfully bid and a construction contract has been executed with Quality Enterprises. A Notice To Proceed will be issued for 9/4/2018. Construction schedules will be phased in different areas of the project, but in total the construction will begin in September 2018 and be completed by June 2019. A public meeting will be held on September 13, 5:00 PM at Town Hall to present project information and answer questions. 
  • 7/20/2017 - Project is shovel-ready, but construction has been deferred until funding is available . Projected groundbreaking is September, 2018.
  • 9/30/2016 - A Request for Proposals for the Nassau Street Redevelopment and Pope Avenue and Lagoon Roads intersection Projects was issued with a solicitation deadline of October 27, 2016.
  • 9/16/2016 - An Invitation for Bids for the South Forest Beach Drive Pathway and Tanglewood Drive Pathway Improvement Projects was issued. The solicitation deadline is October 12, 2016.
  • 7/15/2016 - Request for Proposal for Coligny Redevelopment Project was issued including both the road projects (Nassau Street, Lagoon Road Extension, Pope/Lagoon Extension, South Forest Beach) and the park project. The solicitation deadline is August 25, 2016.
  • 6/15/2016 - The Planning Commission approved application for Public Project Review for additional road improvements including a fully signalized intersection at Pope Avenue and Lagoon Road.
Project Photos & Videos
  • Photo of Median Removal on Pope Avenue
    Median Removal on Pope Avenue - 1/11/2019
  • Photo of Tree Removal on Pope Avenue
    Tree Removal on Pope Avenue - 1/11/2019
  • Photo of TreeRemoval - Nassau Street
    TreeRemoval - Nassau Street - 12/11/2018
  • Photo of Pope Avenue Pavement Patching
    Pope Avenue Pavement Patching - 12/12/2018
  • Photo of Asphalt Shoulder Patchwork on Pope Avenue
    Asphalt Shoulder Patchwork on Pope Avenue - 12/6/2018
  • Photo of Tree Removal at Coligny Beach Parking Lot
    Tree Removal at Coligny Beach Parking Lot - 12/6/2018
  • Photo of Tree Removal Work at Coligny Beach Parking Lot
    Tree Removal Work at Coligny Beach Parking Lot - 12/6/2018
  • Photo of Tree Clearing for Powerline Relocation Work
    Tree Clearing for Powerline Relocation Work - 11/30/2018
  • Photo of Coligny Roadway Redevelopment and Pope Avenue Resurfacing Project Sign
    Coligny Roadway Redevelopment and Pope Avenue Resurfacing Project Sign - 10/29/2018
  • Photo of Coligny Area Aerial Photo
    Coligny Area Aerial Photo - 9/26/2018
  • Photo of Tanglewood Drive Pathway Before Construction
    Tanglewood Drive Pathway Before Construction - 9/25/2018
  • Photo of South Forest Beach Drive at Tanglewood Before Construction
    South Forest Beach Drive at Tanglewood Before Construction - 9/25/2018
  • Photo of South Forst Beach Pathway Location Before Construction
    South Forst Beach Pathway Location Before Construction - 9/25/2018
  • Photo of South Forst Beach Pathway Location Before Construction
    South Forst Beach Pathway Location Before Construction - 9/25/2018
  • Photo of Pope Avenue and Lagoon Raod Before Constructution
    Pope Avenue and Lagoon Raod Before Constructution - 9/25/2018
  • Photo of Entrance Coligny Beach Parking Lot Before Construction
    Entrance Coligny Beach Parking Lot Before Construction - 9/25/2018
  • Photo of Nassas Street Looking at Pope Before Construction
    Nassas Street Looking at Pope Before Construction - 9/25/2018
  • Photo of  Nassau Street Looking at Deallyon Before Construction
    Nassau Street Looking at Deallyon Before Construction - 9/25/2018
  • Photo of Nassau Street and Tanglewood Drive Before Construction
    Nassau Street and Tanglewood Drive Before Construction - 9/25/2018