USCB Hospitality Management Program Facility

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

Development of an educational facility for the USCB Hospitality Management Program, the Osher Lifelong Learning Institute (OLLI), the Event Management & Hospitality Promotion Program, and other higher education and adult education programs.


In December 2013 Town Council, working with officials from the University of South Carolina Beaufort (USCB), directed staff to engage the Town's consultants to relocate the proposed USCB Hospitality Management and Osher Lifelong Learning Institute (OLLI) facility from the Coligny District to a new site in the Office Park Road area. Six parcels were assembled for the project including property currently owned by the Town of Hilton Head Island, as well as the Kiawah building, Carolina Office Park, and Time-Warner. The Town's traffic consultant, SRS Engineering, completed an assessment of traffic impacts associated with development of the new educational facility including a comparison of what could potentially be developed on the site (under the current Zoning) versus the proposed development of the USCB Hospitality Management and OLLI facility. Recommendations include improvements to the Pope Avenue at Office Park Road/New Orleans Road intersection and enhancements at the Greenwood Drive at Office Park Road intersection.

Based on the USCB program, LMO requirements, site conditions, and in conjunction with the traffic and parking assessments, the consultant team prepared a Preliminary Master Plan for the USCB-Office Park Road facility.

The Preliminary Master Plan includes a 2-story Hospitality Management Academic Building (+/- 40,000 s.f.), an OLLI building (+/- 7,200 s.f.) with a 100-seat tiered classroom, and a Student Café. The plan also includes +/- 300 parking spaces broken into smaller lots and buffered with trees, a leisure trail network with connections to existing multi-purpose pathways, outdoor gathering spaces, and intersection improvements.

The Town and University officials are currently working on drafting a Memorandum of Understanding (MOU) that will outline development provisions and operation of the educational facility. Additionally the Town's onsultants are working with new survey and wetland data to update plans and bring the project cost within budget.

The project budget has been set at $24.5 million and will be jointly funded by the Town, it's TIF partners including Beaufort County, the Beaufort County School District, and the Hilton Head Island PSD, and will include contributions from the University of South Carolina. Depending on various required approvals and construction schedules, the facility could open for classes in 2018.

Due to the magnitude of this project, we have provided a significant amount of additional information in a special section of our website. Please follow the links below for more in depth information regarding the University of South Carolina Beaufort (USCB) Hospitality Management Facility.


Additional Documents



Projected Project Schedule:  Demolition of the Carolina Complex and Time Warner Building is anticipated to start in early February 2016

Projected Construction Start Date:  April 2017

Estimated Completion Date:  September 2018

Project Engineer:  

Thomas & Hutton (Conceptual)
Andrews Engineering (Detailed Design)

Project Architect:  

Wood+Partners (Landscape Architect)
Watson Tate Savory (Conceptual)
Liollio Architects (Detailed Design)

Construction Contract Awarded To:  Fraser Construction

Funding Sources:  TIF and USCB through the Beaufort-Jasper Higher Education Commission and the University of South Carolina Development Foundation.

Estimated Cost of Project:  +/- $24.5 million

Project Manager:  

Jennifer Ray email icon, Urban Designer, 843-341-4665


Project Updates
  • 9/28/2018 -
    • Construction trailer and fence have been removed.
    • Installation of landscaping and irrigation system is underway. Approximately 35% complete.
    • Front entrance drive has been formed and is ready for paving.
    • Sidewalks from parking lot to front entrance have been poured.
    • Building fa├žade is complete.
    • Carpet and ceiling installation on second floor is complete.
    • Equipment and furniture for Teaching Kitchen is being installed.
    • Counter tops and services for Beverage Lab is being installed.
    • Furniture and cabinetry for Biology Lab will be delivered next week.
    • Store front and glazing installation is complete.
    • Interior gypsum board 100% complete.
    • Food service equipment and counters for Cafe are being installed.
    • Plumbing fixtures and cold water dispensers are being installed.
    • HVAC systems and electric power systems are operational.
    • Light systems are 85% complete.
    • AV/IT Teaching equipment 75% complete.
  • 9/28/2018 - Quarterly project update provided by USCB pdf icon
  • 8/22/2018 -
    • Tabby columns and board wood decking are complete.
    • Front concrete steps have been poured.
    • Parking lot pavers and sidewalks are 75% complete.
    • Landscaping is being installed.
    • Main electrical power has been connected to the building.
  • 7/5/2018 - Quarterly project update provided by USCB pdf icon
  • 4/27/2018 - Interior framing is complete. Windows are installed. Metal roofing installation is underway and 35% complete. Mechanical, electrical, and plumbing rough-ins are 95% complete. Brick veneer installation is underway and is 50% complete.

Project Photos & Videos
  • Photo of USCB Hospitality Management Program Facility Construction
    USCB Hospitality Management Program Facility Construction - 9/28/2018
  • Photo of USCB Hospitality Management Program Facility Construction
    USCB Hospitality Management Program Facility Construction - 9/28/2018