Media Release

2018 Post-Hurricane Matthew Dune Restoration Project Progress Update

Release Date: May 15, 2018

Contact Information:
Scott Liggett email icon , Director of Public Projects and Facilities, 843-341-4776, Fax: 843-842-8587


Work to install sand fencing along all portions of the beach is complete. The Town's dune planting contractor, Earth Balance, began work on May 14, 2018 at Fish Haul Beach Park. The next section to be installed will be in Port Royal Plantation between Beach Markers 124 and 130. Work will progress southward until all areas that have had fencing installed are planted. Barring weather interruptions, the contractor expects to be finished in about two weeks.