Beach Renourishment Phase I Project Update 15

Construction activities at Pine Island, Port Royal and Islanders Beach Park

November 14, 2025

This Week's Progress (November 8-14)

Marinex Construction installed over 133,000 cubic yards of sand onto the beach along the Port Royal Sound, also known as the heel of Hilton Head Island.

Cape Romain Contractors worked on the breakwater structures at Pine Island Beach, a project that will take several months to complete.

Looking Ahead (November 15-21)

Marinex Construction will continue pumping sand onto the beach along the Port Royal Sound.

Cape Romain Contractors will continue working on the breakwater structures at Pine Island Beach. Pine Island Beach remains closed during this phase.

Please be mindful of the following:

Stay Connected


Note: To view this news release in Spanish or other native languages, choose your appropriate language from our dropdown menu on the upper right side of our website page.

Nota: Para ver este comunicado de prensa en español u otros idiomas nativos, visite hiltonheadislandsc.gov y elija el idioma apropiado de nuestro menú desplegable en el lado superior derecho de la página de inicio del sitio web.

Contact
Carolyn Grant, Communications Manager
843-341-4618
CarolynG@hiltonheadislandsc.gov