Beach Renourishment Phases 1 & 2 Project Update 22

Construction activities in Palmetto Dunes area

January 9, 2026

This Week's Progress (January 2-9, 2026)

Marinex Construction continued pumping operations, placing over 92,000 cubic yards of sand in the central part of the island, including beach areas along Palmetto Dunes. Work is progressing south.

Cape Romain Contractors resumed work on the breakwater structures at Pine Island Beach on Jan. 3, after a brief holiday pause. This project will take several months to finish. Pine Island Beach remains closed during this phase.

Looking Ahead (January 10-16, 2026)

Marinex Construction will continue working on a portion of the central Island beach in the Palmetto Dunes area and begin mobilizing approximately 18,000 feet of pipe to secure sand from Gaskin Banks.

Cape Romain Contractors will continue working on the breakwater structures at Pine Island Beach, weather permitting.

Early January 2026

The beach tilling at Fish Haul and the Heel will commence in early January. Once the tilling is complete, the sidewalk will be repaired at Fish Haul. Once that is done the project at these portions of the beach will be complete.

Please be mindful of the following:

Stay Connected

Thank you for your patience and support as we work together to enhance and preserve the beauty of our island's shoreline!


Note: To view this news release in Spanish or other native languages, choose your appropriate language from our dropdown menu on the upper right side of our website page.

Nota: Para ver este comunicado de prensa en español u otros idiomas nativos, visite hiltonheadislandsc.gov y elija el idioma apropiado de nuestro menú desplegable en el lado superior derecho de la página de inicio del sitio web.

Contact
Carolyn Grant, Communications Manager
843-341-4618
CarolynG@hiltonheadislandsc.gov