2025 Beach Renourishment Project Timeline

The following timeline may be subject to change depending on external factors beyond the Town's control.

  • Phase 1 - Port Royal (the Heel), Fish Haul and Pine Island
    • Contractor mobilizes in July 2025.
    • August 6, 2025 thru August 15, 2025 - Fish Haul area
    • August 15, 2025 thru September 11, 2025 - Pine Island
    • September 15, 2025 thru November 13, 2025 - Port Royal (The Heel)
  • Phase 2 - Central Island, South Island and South Beach
    • November 13, 2025 thru February 14, 2026 - Central Island including beach areas along Palmetto Dunes
    • February 14, 2026 thru May 8, 2026 - South Island and South Beach areas .
  • Phase 3 - Pine Island Breakwater Structures
    • Schedule to be determined - anticipated in 2026

* Timeframes are subject to change

Project Fill Placement Areas

Map of Hilton Head Island with lines showing fill areas on coastline


View the Project Maps